Installation requirements for piston-feeding centrifugal machines


summary : Piston pusher centrifuges are susceptible to significant oscillations due to factors such as fluctuations in the concentration of the suspension. To mitigate the impact of these oscillations on the building structure, vibration-damping foundations should be used during installation. This involves securing the centrifuge to a vibration-resistant base made of reinforced concrete or cast iron weighing several to tens of tons via foundation bolts. Vibration-damping pads are then used to isolate this base from the floor.

  Plunger discharge centrifuges are susceptible to significant oscillations due to factors such as fluctuations in the concentration of the slurry. To mitigate the impact of these oscillations on the building structure, vibration-damping foundations should be used during installation. This involves securing the centrifuge to a vibration-resistant base made of reinforced concrete or cast iron weighing several to over ten tons via foundation bolts. Vibration-damping pads are then used to isolate this base from the floor.

  Sufficient protective space should be provided around the installation site of the plunger discharge centrifuge, especially a larger space on the door side. Consider the space and orientation required for removing the drum and main shaft from inside the centrifuge when replacing the main bearing. Lifting equipment should be installed directly in front of the centrifuge to facilitate maintenance lifting.

  During the installation of the piping for a plunger discharge centrifuge, the feed pipe between the thickener or hydrocyclone and the centrifuge should be short, straight, or have a large angle. Changes in diameter should be smooth to prevent blockages, ensuring the smooth passage of thick materials. A flexible connection should be provided between the feed pipe and the centrifuge's inlet flange to prevent damage to the connection pipe due to centrifuge oscillations. If the solid content of the slurry is less than 30%, a thickening device must be added to the feed pipe to ensure the feed concentration of the slurry and the normal operation of the centrifuge. Because the centrifuge door must be opened to replace the screen and adjust the gap between the pusher and the screen, the connecting pipes on the door (such as the feed pipe, washing pipe, etc.) should be installed in a way that does not hinder the opening of the door, facilitating daily maintenance and operation.

  To achieve optimal separation results, a gas-liquid separator must generally be installed at the discharge port of the centrifuge to discharge a large amount of entrained gas. The gas discharge receiver should be vertically installed, with a height greater than 2m to ensure smooth filtrate discharge; the solid outlet should remain unobstructed and free from blockages.

  Washing pipes and flushing pipes (water temperature should be close to the material temperature) should be connected before use and ensured to be free from blockages and leaks. Suggestion: Washing water should use a separate water pipe, and each washing part should be controlled by a separate valve; flushing water and cooling water should also use separate water pipes and be controlled by valves.

  The weight of the piping and other auxiliary equipment should not be added to the centrifuge; other supports should be used for support. A feed valve should also be installed before entering the centrifuge to control the amount of feed.

  The main motor should at least use a star-delta reduced-voltage starter or soft starter, and should not be started directly to avoid damage to the centrifuge components.

  Before starting, check: whether the screws of each part of the machine are loose; whether any items are left in the drum; whether the tension of the V-belt is appropriate; whether the electrical system is reliably installed, whether the main motor and oil pump motor are interlocked and whether the direction of rotation is correct; whether the hydraulic oil has reached 2/3 of the level gauge; whether the cooling water valve of the oil cooler is open. Also check if the drum can rotate freely; after checking that everything is normal, you can prepare to start.